HYC50 - Operation and Installation Guide
Version 2-2
Page 66 of 102
4 HYC50 installation and commissioning
All rights reserved. Reproduction of this document, even in part, is only permitted with the approval of alpitronic Srl.
Fix the supplied signal cable passage to the third mounting point of the HYC50 with four
screws (4x M4x18).
Notice
For detailed information on the use of the signal cable passage, consult
the "Extensive step-by-step installation guide" available on the hyperdoc
document platform.
Tighten the screw with a torque wrench (4 Nm).
Figure 49: Third attachment point