INSTALLATION
IEPMU01 AND IEPMU02 POWER MOUNTING UNIT INSTALLATION
I-E96-506B1 3 - 17
19. Use a voltmeter to measure 120/240 VAC power at TB1.
20. Turn the PEP circuit breakers on.
NOTE:
Before doing Step 21, verify that switch and jumper settings
on the power modules are correct. Refer to Table 3-3 for settings.
21. Install the required number (calculated from SIZING THE
MODULAR POWER SYSTEM in Appendix B) of IEPAS02 and
IEPAF02 power modules in the PMU card cage, one at a time.
Slide one power module along the guides until it is seated in
the PMU backplane.
22. Turn the 2 latching screws until they lock. Verify that the
status LED turns green on each power module. If it does not,
refer to Section 5.
23. Do not install the process modules at this time. Refer to
RECOMMENDED START-UP PROCEDURES in Section 4,
Steps 5 through 9.