Recommissioning
Instruction handbook b maXX BM5500, BM5600, BM5700
Document No.: 5.13008.10 Baumüller Nürnberg GmbH
300
of 314
12.6
12.6 Recommissioning
Execute commissioning as with a new device, refer to
ZMountingfrom page 141, ZInstallationfrom page 159.
.
CAUTION!
Recommissioning without forming of the capacitors.
From six months storage period on, the capacitors are destroyed during commission-
ing if they are not formed beforehand
m Reform the DC link capacitors:
n by supplying the device ready-to-operate for at least one hour with supply volt-
age
n but do not transmit a pulse enable during this time.
m Consider, that it is imperative, to connect the accordingly prescribed line commu-
tating reactor for this forming procedure.Devices, where no line commutating reac-
tor is necessary can directly be supplied with mains voltage.