Programmable AC/DC Electronic Load 63800 Series Operation & Programming Manual
5. Press CC to return to main screen of DC mode.
6. High current DC Source settings are shown as Table 10-8, switch DVM2 measurement
terminal to Rear. Please follow the model under CC mode to set loading current & I
p(max).
According to the model to confirm if the values of DVM meet to that in Table 10-8.
Table 10-8
Model
I Ip(max)
100 50
54
63802
108
63803
135
63804
10.5.2 CC Mode Operation & Measurement Verification
1. Press CC to return to main screen of DC CC mode.
2. High current DC Source settings are shown as Table 10-9. Please follow the model under
CC mode to set loading, S.R. & I
p(max). According to the model to confirm if the values of
Meter & Load meet to that in Table 10-9.
Table 10-9
Source Setting Load Setting
Model
Voltage (V)
Current (A)
Current (A)
100 50
5
100
54
4.959~5.041
63802
108
63803
5
135
4.905~5.095
63804
10.5.3 CR Mode Operation Verification
1. Press CR to return to main screen of DC CR mode.
2. High current DC Source settings are shown as Table 10-10. Please follow the model
under CR mode to set R value & I
p(max). According to the model to confirm if the values of
Meter & Load meet to that in Table 10-10.