Powering down/up applications (examples)
Servicing the Network Management Module – 186
4. Set the OS shutdown duration to the time needed for your server to shutdown gracefully.
This will make sureIPPshutdowns your servers before the load segment is powered down.
As a result, it will define the overall shutdown sequence duration for each load segments.
4.3.2.4 Step 3: Power outage policy settings
4.3.2.4.1 Objective
Use load segment policies to define shutdown sequencing.
4.3.2.4.2 Resulting setup
1. Navigate toContextual help>>>Protection>>>Shutdown on power outagepage on the Network Module
2. Set Primary and Group 1 to:Customand set it to end shutdown sequence 180s before the end of backup time.
For examples of Power outage policy, see the following sections:
Maximize availability policy example
Immediate graceful shutdown policy example
Load shedding policy examples
Custom policy examples