SRR section Settings Possible values
Scheduled shutdown schedule enabled true/false
scheduler 1: Primary
2: Group 1
3: Group 2
recurrence 0: once
1: every day
2: every week
shutdownTimeStamp [timestamp (unix)]
restartTimeStamp [timestamp (unix)]
3.4.4.4.1 Additional information
3.4.4.5 Troubleshooting
Action not allowed in Control/Schedule/Power outage policy
Symptom
Below message is displayed when you access the Control, Schedule or Power outage policy page.
This action is not allowed by the UPS.
To enable it, please refer to the user manual of the UPS and its instructions on how to configure the UPS settings and allow
remote commands.
Possible Cause
1- Remote commands are not allowed due to the UPS configuration (see the action below)
2- The UPS does not support remote commands.
Action
Refer to the UPS user manual and its instruction on how to configure the UPS settings and allow remote commands.
Example: UPS menu Settings>>>ON/OFF settings>>>Remote command>>>Enable.
For details on Save and Restore, see the Save and Restore section.