multi N/C 2100S Transport and storage
105
9.2 Storage
NOTICE
Environmental influences and condensate formation can destroy individual components
of the analyzer!
The analyzer must only be stored in acclimatized rooms. The atmosphere must be low in
dust and free
from aggressive vapors.
If the analyzer and add-on devices are not positioned immediately after delivery or are
not required for a prolonged period of time, they should best be stored in their original
packaging. A suitable desiccant should be added to the equipment to prevent damage
from moisture.
The following requirements are placed on the climatic conditions in the storage room of
the analyzer:
Temperature range: +5 °C to +55 °C
max. humidity: 10 % to 30 %
Air pressure: 0,7 bar to 1,06 bar
9.3 Recommissioning after transport or storage
9.3.1 Assembling the analyzer after transport or storage
When positioning the analyzer observe the notes in section "Site requirements" p. 41.
Assemble the components of the analyzer as follows:
1. Carefully remove the basic device, accessories and any add-on devices from the
transport packaging. Do not damage the transport packaging!
2. Position the analyzer at the intended location.
3. Remove the adhesive tape at the top cover and the side walls, remove the top cover,
put it safely aside, and open the doors.
4. Open the left side wall,
• Unscrew the four fastening screws; the screws are undetachable and remain in
the wall.
• Disconnect the grounding conductor connection and put the side wall safely
aside.
5. Remove all remaining adhesive tape and protective bags.
6. Install the halogen trap and water traps (see sections "Replacing the water traps"
p. 69 and "Replacing the halogen trap" p. 72).
7. Install the combustion furnace (see section "Installing the combustion furnace" p. 84).