CHAPTER 3
Small Configuration
Installing the 19-Inch (SFD5) DCM Shelf
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
3-58
Fujitsu and Fujitsu Customer Use Only
Install the SFD5 shelf as follows:
Step Task
1 Unpack the SFD5 shelf from the shipping container. The DCM units do not need to be
removed from the DCM shelf if they are already installed. The shelf can hold up to two DCM
units.
2 Is the SFD5 shelf to be installed in a 19-inch relay rack?
If YES:
Proceed to Step 3 [p. 3-58].
If NO:
Proceed to Step 9 [p. 3-60].
3 Get the flange kit for 19-inch rack mounting. Table 3-5 [p. 3-56] lists the flange kit part
numbers.