CHAPTER 4
ETSI Configuration
Installing Power and Ground Cables
FNC-7500-0061-200
Issue 1, May 2009
FLASHWAVE 7500 Release 6.1
Equipment Installation
4-66
Fujitsu and Fujitsu Customer Use Only
4.13.2 Installing Power and Ground Cables
SUBTASK PAGE
This subprocedure includes the following subtasks: Procedure
Identify Cabling Schematic. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-66
Disconnect Power from PDP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-67
Install Shelf Power Harnesses A1 and B1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-67
Install Shelf Power Harnesses A2 and B2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-68
Install Frame Ground Cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-70
Final Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-70
Use this procedure to install power, ground, and alarm cabling for a rack of FLASHWAVE
7500 ETSI Configuration equipment.
DANGER:
Use properly insulated tools and do not allow tools, cables, or other metal objects to
connect across terminals. At this point, –48 V DC power has been applied to the PDP, and
improper handling may result in personal injury, damage to equipment, or both. Fujitsu
recommends that office power be removed from the rack using local procedures.
Note: Ensure that all cables installed in this procedure are properly bundled, laced, and secured
to the rack in accordance with local procedures. Connectors should be secured in place using
connector retaining screws.
Install power, ground, and alarm cables for one rack of FLASHWAVE 7500 ETSI
Configuration equipment as follows:
Identify Cabling Schematic
Step Task
1 If you have not already done so, review the reference material presented in Section 4.13.1,
Reference Material [p. 4-62].
Revision 1, June 2009