Issue 1
4-4 Pressure indicator operation (MC 620-IS) K0460 - [EN] English
• When all the software selections are complete, make the
applicable pressure and electrical connections. Examples:
Measure pressure (Section 4.4.4).
4.4.2 Set-up a Leak Test
1) Set the Utility Set the Utility to Leak Test (Section 2.8.6).
2) Set the Leak Test
options
When setting the Utility to Leak Test, set these options:
Wait Time: The time before the test starts in
hours:minutes:seconds (hh:mm:ss).
Test Time: The period of the leak test in
hours:minutes:seconds (hh:mm:ss).
Note: To set the Leak Test options, have a pressure module
correctly installed (Section 4.2.1).
1
3
4
Select Leak Test Select Test Time
Steps 5 and 6: Set the Test Time
+ Set the Wait Time.
TAP the window
(Maximise)
Select Settings
5
6
7
Start the test and let it
complete.
Go back to the Home window. Start the test
when the pressure system is set-up.
Stop the test (with no results)