Hardware options installation 101
M.2 SSD enablement board installed in the PCIe3 x8 riser board slot 4
d. Install the PCI riser cage (on page 36).
e. Open the cable management holder (on page 32).
f. Connect the SATA cables to the M.2 SSD enablement board and the system board.
g. Close the cable management holder (on page 34).
h. Secure the extra length of the SATA cables in the cable management holder.
8. Install the air baffle (on page 32).
9. Install the access panel (on page 30).
10. Install the server into the rack (on page 45).
11. Power up the server (on page 19).
To manage and monitor the SSD modules, use Smart Storage Administrator
(http://www.hpe.com/servers/ssa).
Installing an SSD module on the M.2 SSD enablement board
1. Power down the server (on page 19).
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.

Table of Contents

Other manuals for HP Apollo 4200 Gen9

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the HP Apollo 4200 Gen9 and is the answer not in the manual?

HP Apollo 4200 Gen9 Specifications

General IconGeneral
BrandHP
ModelApollo 4200 Gen9
CategoryServer
LanguageEnglish

Related product manuals