Site Planning Checklists
This section provides reference checklists for site preparation.
“Preparation Checklists” on page 169
Preparation Checklists
Complete the checklists in this section to ensure the site is prepared for the server.
“Access Route and Data Center Checklist” on page 169
“Data Center Environment Checklist” on page 170
“Facility Power Checklist” on page 171
“Rackmount Checklist” on page 172
“Safety Checklist” on page 173
“Auto Service Request Checklist” on page 173
“Logistics Checklist” on page 174
Access Route and Data Center Checklist
Review the following facility checklist before installing the server.
TABLE 13
Access Route and Data Center Room Checklist
Data Center Room Considerations Yes No N/A Comment
Has the access route been checked for clearances of the
packaged equipment?
Do all the doors and entry ways conform to the width and
height requirements for transportation, including the width
of the unpacked unit?
Are there any ramps, stairs, or thresholds that are in the
moving path for the new hardware?
Site Planning Checklists 169

Table of Contents

Other manuals for Oracle X5-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Oracle X5-2 and is the answer not in the manual?

Oracle X5-2 Specifications

General IconGeneral
Number of Processors2
Cores per ProcessorUp to 18
Form Factor2U Rackmount
ProcessorIntel Xeon E5-2600 v3
MemoryUp to 768 GB DDR4
Power Supply1200W
Operating SystemOracle Linux, Oracle Solaris
Network4 x 10Gb Ethernet ports

Related product manuals