PCX SMS AND PCX 256 SYSTEM MANUAL
Page: 90 RINS871-3
Enter the number of the inputs you wish to soak test
and press O. The input number shows on the
scrolling list. Repeat for each input to be tested. To
remove an input from the list, enter its number again.
Press the P key.
Enter the number of days the soak test will last. Press
the Okey.
Enter the number of days the soak test will revert to in
the event a soak input is triggered during testing.
Press the Okey. ‘Test Control’ will be displayed,
press the P key.
Test Bell?
To Test the Bell press the Okey.
All outputs programmed as either Bell or Strobe will
be tested. Press the P key to stop the test. ‘Test
Bell’ will be displayed, press the P key.
Do Battery Load Test?
To perform a Battery Load Test, press the Okey.
The Battery Load test will be started.