Commissioning (software)
5.7 Commissioning modes
Control Units CU240S
Operating Instructions, 11/2006, A5E00766042B AA
5-53
Upload a parameter set with an MMC
Prerequisites
To perform a series commissioning with the MMC the following conditions must be fullfiled:
● Supply voltage is active for the upload inverter
● The upload inverter is in "Ready State".
Note
Before uploading, the parameters will be copied from RAM to EEPROM
Parameter Description (Parameter name and factory setting (if not variable) in bold) Setting
Insert the MMC to the inverter - for the parameter set to be uploaded, perform the following
steps:
P0010 = 30 Commissioning parameter*
0: Ready
1: Quick commissioning
2: Inverter
30: Factory setting, parameter transfer
95: Safety commissioning (for CUs with fail-safe functions only)
P0804 = ? Select Clone file
0: clone00.bin
…
99: clone99.bin
Note: Via P0804 the name of the clone file can be selected. Theoretically up to 100 (0 … 99)
parameter sets can be stored on an MMC.
P0802 = 2 Transfer data from EEPROM
0: Disabled
1: Start OP Transfer
2: Start MMC Transfer
If the upload has been completed successfully, P0010 and P0802 will be set to 0 and the
"RDY" LED is on.
If the upload has failed, F0061 (MMC-PS not fitted) will be displayed, LED "SF" (red) is on.
In this case insert an MMC and attempt another upload.
After a successful upload remove the MMC from the upload inverter.