Section 1 – Scheduled Maintenance Scheduled Maintenance Inspections
1.6-9 Optional equipment (B)
Do the inspection that follows, and make sure:
1
Generator
â–ª
There are no loose or missing parts, and there
is no visible damage.
â–ª
All hoses are correctly tightened and there is
no sign of hydraulic leakage.
2
Flashing amber light
â–ª
The lamp is correctly attached, and there is no
visible damage.
3
Welder
â–ª
The welder and the welder tray are correctly
attached.
â–ª
There are no loose or missing parts, and there
is no visible damage.
â–ª
There are no loose wires or missing fasteners.
4
Cold or arctic weather package
â–ª
The heater plugs are correctly attached with
no visible damage.
â–ª
There is no sign of engine oil leakage.
5
Tool tray
â–ª
The tray is correctly attached with lock-pins,
and there is no visible damage.
6
Glazier
â–ª
There are no loose or missing parts, and there
is no visible damage.
7
Pipe rack
â–ª
There are no loose or missing parts, and there
is no visible damage.
6
21 4
7
3
5
To order go to Discount-Equipment.com

Table of Contents

Other manuals for Skyjack SJ63 AJ+

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Skyjack SJ63 AJ+ and is the answer not in the manual?

Skyjack SJ63 AJ+ Specifications

General IconGeneral
BrandSkyjack
ModelSJ63 AJ+
CategoryBoom Lifts
LanguageEnglish

Related product manuals