Safe torque off function 237
Grounding of protective shields
Ground the shield in the cabling between the activation switch and the control
board at the control board.
Ground the shield in the cabling between two control boards at one control board
only.
Operation principle
1. The Safe torque off activates (the activation switch is opened, or safety relay
contacts open).
2. The STO inputs IN1 and IN2 on the drive control board de-energize.
3. The control board cuts off the control voltage from the drive IGBTs.
4. The control program generates an indication as defined by parameter 31.22 STO
indication run/stop, see ACS580 standard control program firmware manual
(3AXD50000016097 [English]).
The parameter selects which indications are given when one or both Safe torque
off (STO) signals are switched off or lost. The indications also depend on whether
the drive is running or stopped when this occurs.
Note: This parameter does not affect the operation of the STO function itself. The
STO function will operate regardless of the setting of this parameter: a running
drive will stop upon removal of one or both STO signals, and will not start until
both STO signals are restored and all faults reset.
Note: The loss of only one STO signal always generates a fault as it is interpreted
as a malfunction of STO hardware or wiring.
5. Motor coasts to a stop (if running). The drive cannot restart while the activation
switch or safety relay contacts are open. After the contacts close, a new start
command is required to start the drive.
Start-up including acceptance test
To ensure the safe operation of a safety function, validation is required. The final
assembler of the machine must validate the function by performing an acceptance
test. The acceptance test must be performed
at initial start-up of the safety function
after any changes related to the safety function (circuit boards, wiring,
components, settings, etc.)
after any maintenance work related to the safety function.
Competence
The acceptance test of the safety function must be carried out by an competent
person with adequate expertise and knowledge of the safety function as well as