1.4 Configuration Safety Checklist
Use this checklist to ensure you have completed all tasks required for BS5839 Pt.8 compliance.
“Have I …. Section Page Step(s) Check (9)
Correctly set-up and commissioned AC surveillance on
monitored amplifiers (including all standby amplifiers)?
6 20 7
Correctly set-up and commissioned DC surveillance on
monitored speaker circuits?
6 21 8
Enabled leakage detection on monitored amplifiers? 6 22 9
Correctly enabled Sleep Mode? 6 22 14
Correctly configured Fire Microphone Input Gains? 9.3 39 6
Correctly configured Fire Microphone Input OP Relative
gains?
9.3 39 7
Enabled surveillance monitoring on Fire Microphone
inputs?
9.3 39 8
Correctly configured Fire Microphone Input EQ? 9.3 40 9
Correctly assigned (lower) priorities to routine functions,
e.g., paging microphones?
9.4 42 12
Correctly configured Fallback DVAs in the event of
Network Failure?
9.5 43 13
Correctly configured DVA gains? 10.3 64 5
Correctly configured DVA O/P Relative Gains? 10.3 64 6
Correctly assigned priorities to the DVA messages? 10.4 65 7
Correctly assigned (lower) priorities to routine functions,
e.g., background music?
11.4 72 10
Correctly set up Output Gains? 13 76 3
Correctly set up Output EQ? 13 76 4
Correctly set and enabled output surveillance? 13 77 5
Correctly set up Output Override Gains? 13 77 6
16.1 83 1-7
Correctly allocated DVA routing from the Fire Alarm
triggers?
16.2 86 1-8