Capstone Turbine Corporation • 16640 Stagg Street • Van Nuys • CA 91406 • USA
Installation Guide: Capstone C1000S/C800S/C600S with C1000 Series Controller
480064 Rev C (December 2018) Page 25 of 122
Capstone reserves the right to change or modify, without notice, the design, specifications, and/or contents of this document without
incurring any obligation either with respect to equipment previously sold or in the process of construction.
3.2. Compliance, Standards and Codes
Since the microturbine produces electricity up to 480 V (defined by the National Electrical Code
as low voltage, having 600 V or less), and since it is a gas-powered device, installation usually
requires one or more permits from local regulatory bodies or grid interconnection approval through
the local utility. Capstone microturbines also carry a number of third-party certifications.
Microturbines are fundamentally low emissions generation technology, but may be subject to
exhaust emissions regulations on a local level, national level, or both. Compliance with emissions
regulations usually requires special permits. Check with the local air quality agency early in the
design phase of any project for permitting requirements. More detailed information regarding
microturbine exhaust emissions can be found in the Emissions Technical Reference (Table 1).
Contact your local distributor for best-practice recommendations on air emissions permitting in
your region.
Standards and codes vary by municipality, region, country, and application. For
example, some areas may require a certificate–of–need, zoning permit, building
permit or other site–specific certificate. Check with all local government
authorities early in the planning process to establish requirements. Check back
periodically for updates.
Compliance with all applicable local and national codes is the responsibility of
the installer.
3.2.1. Microturbine Certifications
Capstone products are designed and certified to meet specific standards. The following standards
apply. Refer to the C1000S/C800S/C600S Product Specification (Table 1).
Underwriters Laboratories (UL 2200)
CE Certification
o 2014/30/EU EMC Directive
o 2006/42/EC The Machinery Directive
o 2014/68/EU PED Directive
Compliant with the following grid interconnection standards:
o Underwriters Laboratories (UL 1741SA)
o Bundesverband der Energie- und Wasserwirtschaft (BDEW TR3)
o Verband der Elekrotechnik (VDE AR N 4105)
o Comitato Elettrotecnico Italiano (CEI 0-16)