2  Unit installation
16
SMGB0077 rev.0 - 01/2013
Accessory Quantity Purpose
Drain hose
1
For drain hose connection
Wire clamp
2
Checking pattern
(Cut out from the carton board)
1
For adjusting space of false ceiling opening and 
position of the unit
Applicable panel
Indoor unit Applicable panel
RCI-(1.0-6.0)FSN3
P-AP160NA1 
P-AP160NAE (with motion sensor)
RCI-(1.0-6.0)FSN3Ei P-N23NA
2.1.2  Unit installation
Initial checks
Install the indoor unit with a proper clearance around it paying careful attention of installation direction for the piping, wiring 
and maintenance working space, as shown below. 
Provide a service access door near the unit piping connection area on the ceiling.
Check space between ceiling and false ceiling is enough as indicated below.
Check the ceiling surface is at for the air panel installation work.
Clearance: 
10-20mm
Unit High 
In False Ceiling
Unit HP A(mm)
RCI-1.0 to 2.5HP 248
RCI-3.0 to 6.0HP 298