Figure 5-25 Wizard Startup
● For the initial wizard startup, Last Record is in gray, indicating that operation is not
allowed.
● For a non-initial wizard startup, you can choose Last Record to view the last wizard
startup report.
Figure 5-26 Checking before startup
Step 2 Follow the onscreen instructions to complete the wizard startup.
● If electric heaters and humidiers are not congured, the electric heater
commissioning and humidier commissioning items are not displayed.
● If the heating and
humidication functions are disabled, the electric heater
commissioning and humidier commissioning items cannot be selected.
● All the items are selected by default if you enter the screen for selecting
commissioning items for the
rst time. You can clear commissioning items that
are not required.
● After the fan commissioning, the electric heater commissioning screen is
displayed. Use a clamp meter to measure the current of the cable connected to
the KM4 terminal, enter the value on the screen, and tap Submit within the
time displayed on the screen. The system automatically determines whether
the current of the smart cooling product is within the normal range.
FusionModule2000-S Smart Modular Data Center
User Manual 5 Power-On Commissioning
Issue 07 (2022-09-30) Copyright © Huawei Technologies Co., Ltd. 175