5.3.14.10 Creating an ECC800-Pro on the NetEco
Prerequisites
● You have logged in to the NetEco client using a web browser.
● You have created a smart module in Planning Conguration.
Context
For detailed operations, see
iMaster NetEco Device Installation and Commissioning
Guide (Data Center)
of the corresponding version.
Procedure
1. On the main menu, choose Device Management >
Conguration >
Planning
Conguration. The Planning Conguration page is displayed.
2. On the Planning Conguration page, click Discover in the upper left corner.
3. Click Access to access the Device Integration page. You can add an ECC800-
Pro device to the
specied smart module on the page.
Figure 5-85 Adding an ECC800-Pro device to the smart module
Click OK, and you can view the task information, including Type, Device Name,
Management Domain, Progress, Status, Start Time, End Time, and Detailed
Information in the displayed window.
5.3.15 (Optional) Third-party NMS Management (over SNMP)
5.3.15.1 Connecting a Communications Cable
Procedure
Step 1 Connect a communications cable to the WAN1 port on the ECC800-Pro.
FusionModule2000-S Smart Modular Data Center
User Manual 5 Power-On Commissioning