Path Parameter Setting
Communicati
ons Port
Device
Address
COM1/COM2
Enter the actual device address of the
PDU2000.
3. Click Test Connect to check whether the PDU2000 connects to the ECC800-
Pro properly.
– If the connection is normal, click
Conrm. The device connection
information is displayed in the Number of connected devices list.
– If the connection is abnormal, check whether the cable is properly
connected to the device, whether the device is running properly, and
whether the parameter settings are consistent with the device
parameters.
----End
5.2 Power-On Commissioning for the Cooling System
For details about the power-on commissioning for the cooling system, see the
NetCol5000-A050 In-row Air Cooled Smart Cooling Product User Manual (1350
mm Depth)
and
NetCol5000-A050 In-row Air Cooled Smart Cooling Product Quick
Guide (1350 mm Depth)
.
5.2.1 Power-On
Step 1 Turn on all switches except indoor unit switches QF1 and QF2 in the smart cooling
system.
Step 2 Turn on the upstream power input switch for the smart cooling product.
Step 3 Turn on indoor unit switches QF1 and QF2.
Step 4 After the initial power-on, the Quick Settings screen is displayed. Log in as user
admin.
Figure 5-9 Initial power-on
FusionModule2000-S Smart Modular Data Center
User Manual 5 Power-On Commissioning
Issue 07 (2022-09-30) Copyright © Huawei Technologies Co., Ltd. 154