Figure 3-14 Leveling a smart cooling product cabinet
(1) Level
Step 4 Level other cabinets in the same way.
----End
3.4 Combining Cabinets
Procedure
Step 1 Level the cabinets using a wrench.
NO TICE
Use a measuring tape to check that the vertical distance between the top of
the 2000 mm high cabinet and the oor is 2000 mm (±3 mm). Then use a level
to check that the cabinet is level.
If the leveled height of a cabinet does not meet the requirement, the door of
the cabinet behind it may not be opened or closed properly.
Adjust the base height or use washers to level the IT equipment.
FusionModule2000-S Smart Modular Data Center
User Manual 3 Hardware Installation
Issue 07 (2022-09-30) Copyright © Huawei Technologies Co., Ltd. 49