● Install two cable troughs on the top of the cabinet at the end of a row (PDF)
rst, and then install cable troughs on the top of other cabinets along the
aisle in sequence.
Figure 3-39 Cable trough components
(1) Partition plate (2) Vertical plate (3) Tray
When installing cable troughs, be aware of rPDU cables at the top of the cabinet:
● Install cable troughs above the front door of a cabinet rst. When installing
cable troughs above the rear door, move the cables to the open area of the
cable troughs. After installing cable troughs above the rear door, place the
rPDU cables and industrial connectors inside the cable troughs above the
front door.
● After rPDU cables are placed, bind the cables to the cable trough using cable
ties.
FusionModule2000-S Smart Modular Data Center
User Manual 3 Hardware Installation
Issue 07 (2022-09-30) Copyright © Huawei Technologies Co., Ltd. 70