BEARING CARRIER STEERING DRIVE
7E - 45
8. Heat bearing cone (11) to 135EC (275EF) for 45 minutes. Install
on bearing carrier (12) and bottom. To insure cone is seated,
keep pressure against cone until it cools.
REMARK
For installation of brake carrier, refer to REASSEMBLY and follow
steps from brake carrier installation to end.