Crusher Operation
Finishing Plant Start Up
1. Check that all items are running satisfactorily.
2. Ensure the plant is stable and without undue
vibration. If necessary, reposition the plant on
󰘰rm, level area with the full length of both tracks
in contact with the ground.
3. Check all other aspects of the plant are ready for
the introduction of material.