10-4
11
12
13
13
14
15
14
16
16
17
13
Preparing to Move Plant
11. Remove the fasteners, lift and remove the
handrail sections on the maintenance platform.
12. Remove clips and ladder handrails then fold
side ladders upward and secure with clips.
14. Remove the securing bolts from the pivot
points on the ladder.
15. Fold up the ladder and t the securing chain.
13. Remove the fasteners, lift and remove the
handrail sections on the maintenance platform.
16. Remove the securing pins and carefully
remove the ladder with suitable lifting
equipment .
17. Place the ladder support bracket on the
chassis into the transport position and secure.