Putting into Operation R&S SMB
1407.0812.62 1.12 E-2
Putting into Operation
The following section describes the procedure for putting the instrument into operation. It contains
general safety instructions for instrument operation.
The installation of options and the firmware update are described in Chapter 4 of the Service Manual
(supplied with the instrument on the CD-ROM).
Unpacking the Instrument
! Remove the instrument from its packaging and check the equipment for completeness using the
delivery note and the accessory lists for the separate items.
! Check the instrument for damage.
! If there is damage, immediately contact the carrier who delivered the instrument. In this case, make
sure not to discard the box and packing material.
! The original packaging is also useful for transporting or shipping the signal generator later on.
Setting up the Instrument or Installing it in a 19" Rack
The instrument is designed for indoors use. It can either be set up independently or mounted in a 19"
rack.
A rack adapter (refer to data sheet for Order No.) is required for installation in a 19" rack. The mounting
instructions are supplied with the adapter.
ATTENTION
Risk of overheating!
To less airflow for cooling may cause overheating of the instrument.
Prior to putting the instrument into operation always check for space between the
ventilation holes and the rack casing to get sufficient air supply in the rack.