16
Bench Testing
7UT51 v3
164 PRIM-2330C
6. Click
Close
to close the Test Results dialog box.
7. Click
Close
to close the
Commissioning Tests
window.
8. Select “
4800 Commissioning Tests Stop
”.
9. Select “
4801 Stop the Commission Tests
” and
click
Yes
.
Validate for Other Phases
Connect the test sources to the relay as shown in
Figure 16.4 and Figure 16.5. In each case, re-apply
the test currents and check the metering as described
in the previous procedure.
Figure 16.4
Two
-
Source Through Fault Testing for
Phase B-Gnd Fault on Wye Side
Figure 16.5
Two
-
Source Through Fault Testing for
Phase C
-
Gnd Fault on Wye Side
16.3.3 Three
-
Winding Transformer
Differential Protection
(7UT513 Only)
A 7UT513 relay, protecting three winding
transformers, can be adequately tested by considering
two windings at a time, and testing them like a
two-winding transformer. Test the reference winding
and Winding 2. Then test the reference winding and
Winding 3. Testing Winding 2 and Winding 3 is not
necessary.
To test tertiary transformer differential protection, do
the following:
1. For testing the three-winding transformer
differential protection, this function must be
configured as EXIST (Address 7816) and the
protected object (Address 7801) must be a
3WIND-TRANSF (7UT513 only). Additionally, it
must be parameterized as operative,
On
in
Address 1601.
2. Connect the relay as shown in Figure 16.6.
(assuming the tertiary winding is connected in a
wye configuration.)
Figure 16.6
Two Source Through
-
Fault Testing for
Delta
-
Wye 3 Winding Transformer Protection
3. Follow the same procedure as described earlier in
this section, but use the configuration of the
tertiary winding in place of the secondary winding.