Electrical installation
4.5 Connections
Cabinet Modules NEMA
Manual, 04/2014, A5E03586450A
107
4.5.12.3
Cable routing for Basic Line Modules
For the Basic Line Modules, the customer must carry out the following cabling or connection
work:
Table 4- 15 Checklist for cabling or connection work for Basic Line Modules
Cable routing
Completed?
PROFIBUS cable or PROFINET cable to the Control Unit
DRIVE-CLiQ connections / signal cables to the Control Unit
Signal cables to the customer terminal block –X55
Note:
The "Basic rules for cable routing" and "Preparatory steps" described above must
be observed whenever any cabling or connection work is performed.