1.2.5.6 Commissioning and maintenance
1.2.5.6.1 Commissioning
Before the system is taken into use the safety functions must be tested/validated.
The STO-SBC function shall be activated/deactivated and the reactions shall be monitored (the reaction
depends if used as emergency stop or prevention of unexpected start-up or something else).
1. Safety wiring diagrams and the commissioning test shall be documented and stored (who,what,when)
2. Define maintenance routines according to the need (see chapter maintenance)
1.2.5.6.2 Maintenance
IEC 61800-5-2:2017 requires to have a maintenance test for STO-SBC function. The frequency of testing
depends on the required safety level:
one test per year for SIL 2 , PL d / category 3
one test per three months for SIL 3 , PL e / category 3
The maintenance test can be done by activating STO/SBC function through STO-SBC inputs and observe the
reaction of the system.
Synapticon Documentation
© 2021 Synapticon GmbH | Daimlerstraße 26 | D-71101 Schönaich Documentation v 4.11.0 | Built 2021-07-23 130/887

Table of Contents

Other manuals for SYNAPTICON SOMANET Node 400

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the SYNAPTICON SOMANET Node 400 and is the answer not in the manual?

SYNAPTICON SOMANET Node 400 Specifications

General IconGeneral
BrandSYNAPTICON
ModelSOMANET Node 400
CategoryServo Drives
LanguageEnglish

Related product manuals