Installation Manual _________________________________________________________________
122 _________________________________________________________________ M210485EN-B
0310-048
Figure 109 Connecting the Antenna Cable
Verification
To verify the system, power it up:
1. Connect the battery connector inside QMP202MP.
2. Connect the AC cable to power outlet.
3. Turn the power switch ON inside QMP202MP.
Ceilometer CT25KAM
After switching the AC (mains) power on, you can verify the
operation of CT25KAM Ceilometer with the status LED, see Table 7
below.
Table 7 States of the Status LED in CT25KAM
State Explanation
Red Only the AC cable is connected.
Green Only the DATA&DC cable is connected.
Blinking from
green to red
Both cables are connected, indicating that the operating
voltage and mains power are available.
Red Both cables are connected and the internal heating is on
(likely after start up).