Installation Manual _________________________________________________________________
58 __________________________________________________________________ M210485EN-B
0207-062
Figure 42 Foundation Assemblies for a New Concrete
Pad
7. For the guy wires, fix the foundation bolt (number 2 in Figure
42 above) to the plate with a nut (3). Fix the eye nut (1) to the
other end of the foundation bolt. Level the assembly so that the
top of the bolt will be 40 mm above the concrete in the finalized
block. The eye nut will then be one centimeter above the
finalized concrete pad.
8. Pour in the concrete. Finish the concrete pad.