3-2
P129390-106 Operator Manual Installation Verification
3.1.3 Electrical Service ❑ The protective earth ground must be connected to terminal block
TB-1 in the sterilizer power box.
❑ Three-phase power for the sterilizer must meet specifications on
the equipment drawing.
❑ Verify proper rotation of the vacuum pump by observing pump
rotor shaft.
Important: Three-phase service requires a clearly marked
disconnect with lockout/tagout capability located near the
sterilizer with easy access for maintenance personnel. If more
than one sterilizer is connected to the same supply, each should
be equipped with independent lock/tagout capability,
3.1.4 Sterilizer Final Check ❑ Chamber leveled properly.
❑ Door opens and closes smoothly.
❑ Door locked switches adjusted correctly.
❑ Chamber strainer in place.
❑ Rack and shelves and/or loading carrier operate correctly.
❑ Paper loaded in printer.
❑ Printer ribbon properly installed.
❑ Warranty labels properly applied.
❑ Verify programming and set up support proper configuration of
unit.
3.1.5 Cycle Operation ❑ Unit powers up correctly.
❑ Run Leak Test cycle leak rate is to be less than 1.3 mbar/min
(0.4 mm Hg/minute).
❑ Verify operation of a typical cycle (134° C [273°F] prevacuum).