ASV RC30 - Loader Valve Installation

ASV RC30
117 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Rubber Track Loader
9. Loader/Transmission Controls Disassembly and Assembly
9-9
Loader Valve Installation
Figure 9-34 9-017
1. Position the loader valve against the hydraulic
reservoir.
Figure 9-35 9-016
2. Install the nuts on the four bolts that secure the
loader valve to the hydraulic reservoir.
Figure 9-36 9-015
3. Install the hoses on the end and side of the
loader valve.
Figure 9-37 9-014
4. Install the tubes on the bottom of the loader
valve.
Figure 9-38 9-013
5. Install the tubes on the side of the loader valve.
Figure 9-39 9-012
6. Install the tubes on the top of the loader valve.
7. Add manufacturer-approved hydraulic fluid.