Sliding window
This is the calculation of maximum demand in a specific interval (usually the integration period = 15 
minutes). Once the number is calculated, it is refreshed every minute with the values from the last 15 
minutes. In other words, every minute (this time can be variable) we will have a maximum demand 
number for the last 15 minutes. The result would be 60 values per hour.
P
t
Fixed Window
 Integration period 
 Integration period 
Sliding window
Calculation time
Figure 29: Sliding window.
The CVM-C11 calculates the maximum demand of the following: 
    Current of the L1, L2, L3 and three-phase.
  Three-Phase Active Power.
  Three-Phase Apparent Power.
  Three-Phase Inductive Reactive Power.
  Three-Phase Capacitive Reactive Power.
In the configuration menu, the type of integration is selected, “6.10. TYPE OF INTEGRATION OF THE 
MAXIMUM DEMAND” and the integration period of the maximum demand “6.11.- MAXIMUM DEMAND 
INTEGRATION PERIOD”.
  
 4.2.- DISPLAY
The device has a backlit LCD display showing all the parameters listed in Table 7 ... Table 14.
The display is divided into two areas (Figure 30):
Units and status 
area
Data area
Figure 30: CVM-C11 Display areas.
42
CVM-C11
Instruction Manual