19 – 11
Section 19 • Compressor Sequencing
MicroVission Controller • Operation and Service Manual • Emerson • 35391MV 1.3
Conguration Overview
Other Compressors should be congured rst, and then
congure the Compressor Sequencing device table on
the compressor from user wants to start Sequencing.
The Conguration screen allows the operator to:
1. Enable Ethernet port.
2. Enable / Disable Compressor Sequencing.
3. Assign a compressor name.
4. Assign network name for sequencing.
5. Select Modbus TCP protocol.
6. Assign a unique Ethernet IP address.
Setting up the other Compressors for
Sequencing
1. Log onto each of the compressors one by one and
navigate to the Conguration screen see Figure
19-10.
2. Enable the Ethernet port and select the Modbus TCP
protocol.
3. Set up a unique Ethernet IP address for each
compressor.
4. Set up the Subnet Mask for the IP address.
5. Set up the Gateway address (MUST DO!).
6. Assign a Name for each compressor.
Figure 19-10. Conguration Screen (Page 3) – Compressor Sequencing Setup