Mounting the Switch
Enterasys D-Series Hardware Installation Guide 2-17
Figure 2-14 Installing Power Supplies into the Lockbox Tray
a. Threadthestrapthroughthemountingtrayandaroundthepowersupplyinthe
followingorder:
(1) Throughthebridgeanchorononesideofthepowersupply
(2) Underthepowersupply
(3) Throughthebridgeanchorontheothersideofthepowersupply
b. Wraptheendsofthestrapoverthetop
ofthepowersupplyandfastensecurely.
c. Repeatstep 1onpage 216withanotherhook&loopstraptosecuretheotherendofthe
powersupplytothemountingtray.Finalplacementofpowersuppliesisshownin
Figure 214onpage 217.
2. PlugtheDCpowercordfromthepower
supplyintotheswitchDCpowerreceptaclethatis
appropriateforyourtype ofpowersupply.
•FortheD2PWRsupply,plugintothePWR1AorPWR2Areceptacle.
•FortheD2PWRPOEsupply,plugintothePWR1BorPWR2Breceptacle.
3. PlugtheACcordintothepower
supply’sACreceptacle.
4. (Optional)Ifyouhavepurchasedasecondpowersupplyandwishtoinstallit,repeatstep 1
onpage 216thoughStep 3usingthesecondpowersupplyslotinthetrayandtheunused
PWRreceptacleappropriateforthesupply.RefertoConnectingPowertotheSwitchon
page 226formoreinformationaboutpowerredundancy.
5. PlugeachACpowercordintoadedicated,groundedACoutlet.SeeConnectingPowerto
theSwitchonpage 226forinformationaboutthe initializationprocess.