2.9.2  Cold Load Pickup for SWITCH ONTO FAULT Condition 
In some feeder applications, fast tripping may be required if a fault is already present on the feeder 
when it is energized. Such faults may be due to a fault condition not having been removed from the 
feeder, or due to earthing clamps having been left on following maintenance. In either case, it is 
desirable to clear the fault condition quickly, rather than waiting for the time delay imposed by IDMT 
overcurrent protection. The CLP logic can cater for this situation. Selected overcurrent/earth fault 
stages could be set to instantaneous operation for a defined period following circuit breaker closure 
(typically 200 ms). Therefore, instantaneous fault clearance would be achieved for a switch onto fault 
(SOTF) condition 
2.10  Inrush Current Blocking Function (2ND Harm Blocking) 
When a transformer is initially connected to a source of AC voltage, there may be a substantial surge 
of current through the primary winding called inrush current. This is analogous to the inrush current 
exhibited by an electric motor that is started up by sudden connection to a power source, although 
transformer inrush is caused by a different phenomenon. 
In an ideal transformer, the magnetizing current would rise to approximately twice its normal peak 
value as well, generating the necessary MMF to create this higher-than-normal flux. However, most 
transformers are not designed with enough of a margin between normal flux peaks and the saturation 
limits to avoid saturating in a condition like this, and so the core will almost certainly saturate during 
this first half-cycle of voltage. During saturation, disproportionate amounts of MMF are needed to 
generate magnetic flux. This means that winding current, which creates the MMF to cause flux in the 
core, could rise to a value way in excess of its steady state peak value. Furthermore, if the transformer 
happens to have some residual magnetism in its core at the moment of connection to the source, the 
problem could be further exacerbated. 
We can see that inrush current is a regularly occurring phenomenon and should not be considered a 
fault, as we do not wish the protection device to issue a trip command whenever a transformer or 
machine is switched on. This presents a problem to the protection device, because it should always 
trip on an internal fault. The problem is that typical internal transformer faults may produce 
overcurrents which are not necessarily greater than the inrush current. Furthermore faults tend to 
manifest themselves on switch on, due to the high inrush currents. For this reason, we need to find a 
mechanism that can distinguish between fault current and inrush current. Fortunately this is possible 
due to the different natures of the respective currents. An inrush current waveform is rich in harmonics, 
whereas an internal fault current consists only of the fundamental. We can thus develop a restraining 
method based on the harmonic content of the inrush current. The mechanism by which this is 
achieved is called second harmonic blocking. 
2.10.1  Second Harmonic Blocking Implementation 
Second harmonic blocking can be applied to the following overcurrent protection types: 
•  Phase Overcurrent protection  
•  Earth Fault protection 
Second harmonic blocking is implemented in the GROUP (n) SYSTEM CONFIG column, where (n) is 
the number of the setting group. 
Second harmonic blocking is applicable to all stages of each of the elements.  
The function works by identifying and measuring the inrush currents present at switch on. It does this 
by comparing the value of the second harmonic current components to the value of the fundamental 
component. If this ratio exceeds the set thresholds, then the blocking signal is generated. The 
threshold is defined by the 2ndHarm Thresh setting. 
We only want the function to block the protection if the fundamental current component is within the 
normal range. If this exceeds the normal range, then this is indicative of a fault, which must be