D20E ETHERNET I/O MODULE INSTRUCTION MANUAL GE INFORMATION 101
D20E Ethernet I/O Module
Chapter 8: Powering-up and Testing
a D20E Module
Powering-up an d Testing a D20E Module
This chapter describes how to test for proper operation of a D20E module:
• Prerequisites on page 101
• Power up procedure on page 102
• Test your field I/O on page 102
Prerequisites
Prior to testing of the D20E module, the following tasks must be complete:
1. Earth ground has been connected; see chapter: Preliminary Power Up and Test on
page 83.
2. Field wiring has been completed; see sections:
– D20E-A analog inputs module on page 87,
– D20E-K control outputs module on page 89,
– D20E-S digital inputs module on page 95, and
– D20E-C combination inputs and outputs module on page 97
3. Communication connections have been made; see chapter: Connecting to Devices
and Networks on page 77.
4. Firmware has been configured; see chapter: Configuring the D20E Firmware on page
37.
In addition, DAPserver Studio must be on-hand.
You are now ready to power-up the D20E module and verify that the D20E module is
functioning properly.