3.6.3 Mains connection
A building site main cabinet (according to IEC 60439-4:2004) with fuse
protection of the supply point with min. fusing of 16A slow-to-blow is
required on site.
200 Z with 230 V drive
Supply point: 230V / 50Hz
Fuse protection: 16 A, slow-to-blow
Connect the mains supply line (3 m) for the hoist to the building site
main cabinet.
A rubber hose line measuring at least 3 x 2.5 mm
2
is required for
extending the mains supply line (see accessories) to avoid voltage
drop and therefore any loss in motor performance. For supply lines
over 50 m long, you should use a cable of at least 3 x 4 mm
2
.
If the power supply is poor, unplug any other current consumers.