8.1 Maintenance schedule
Tasks to be carried out
Weekly
Monthly
Quarterly
Annually
Check the braking distance
X
1
Check the gear rack and drive pinion for lubrication and wear
X
1
Check the trailing cable, mains supply cable and control lines
for damage.
X
1
Visual inspection of all defect devices and limit switches
X
Check the rack and drive pinion for wear
X
Check that the ladder interlocking, limit switch approach bar and
ladder ties/bolts are securely attached to the ladder and
building, tighten if necessary.
X
Apply lubricant to the trailing cable
X
Notices present and easily legible
X
Function test of the control (manual control)
X
Check the gearbox oil on the drive
X
Check the gear rack is positioned securely
X
Check motor brakes (air gap and pad thickness)
X
Check the rescue equipment
X
Test overload setting
X
Test the safety gear
X
Check track rollers on the trolley
X
Protective earth testing in accordance with EN 60204, Part 1
Insulation check in accordance with EN 60204, Part 1
1
For increased use or in multi-shift operation, accordingly more frequent.
² Maximum check intervals can be significantly shorter, depending on location of use
and national regulations.