8.2.2 Checks before initial commissioning
Checks at the factory
The following tests have already been carried out at the factory:
Dynamic test with 1.1x useful load.
Electrical tests according to EN 60204
Function tests.
8.2.3 Checks after assembly / daily before starting operation
To guarantee safety when handling the machine, the person appointed
by the operating company is obliged to carry out a daily inspection of
certain machine areas/parts.
Any defects identified must be immediately reported to the supervisor
and rectified. Defects may only be rectified by trained personnel
responsible for maintenance and servicing.
Always carry out visual inspections before function checks. Operation is
prohibited until the defects are rectified.
The following points must be checked daily
Safety check before starting work refer to Chapter 6.2
When descending, check the cable winding of the trailing cable on
the spring-loaded cable reel and manually rewind as necessary.
The spring-loaded cable drum must not be contaminated (free of
snow and ice in winter).
Keep the work area around the GEDA 200 Z clear and clean.
For checks after each installation refer to Chapter 5.6
8.2.4 Recurring checks
GEDA recommends that you carry out a recurring check on an
annual basis. In the event of increased demand (e.g. multiple shift
operation), carry out checks at shorter intervals.