4.4 Verifying the Installation
Cabinet Installation Check
Table 4-15 Cabinet installation check items
No. Check That Check Result
1 The cabinet position is consistent with the
equipment room layout diagram.
□ Passed □ Failed
2 All bolts are tightened, especially the bolts used
for electric connection. Flat washers and spring
washers are installed properly.
□ Passed □ Failed
3 The cabinet is clean and free of dust and other
materials.
□ Passed □ Failed
4 The cabinet is clean and complies with dustproof
requirements.
□ Passed □ Failed
5 The paint on the cabinet exterior is intact.
Promptly repaint the cabinet exterior if necessary
to prevent corrosion.
□ Passed □ Failed
6 The cabinet door and lock work properly. □ Passed □ Failed
7 All labels are correct, clear, and complete. □ Passed □ Failed
8 The cabinet has no waste tape, cable ties, paper,
or packing materials around it.
□ Passed □ Failed
9 All components are properly installed and no
component is left onsite.
□ Passed □ Failed
10 Block empty cable holes using plugs or lids. □ Passed □ Failed
Cable Installation Check
Table 4-16 Cable installation check items
No.
Check That Check Result
1 All cable joints are secured properly, especially the
cable joints between network cables.
□ Passed □ Failed
2 Exposed parts near the wiring terminals and lugs
are wrapped in PVC insulation tape or heat
shrinking tubing.
□ Passed □ Failed
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide