● At a high place with strong winds, install the outdoor unit against a wall to
ensure the normal operating of fans. Install a bae plate when necessary to
prevent the outdoor unit from toppling in strong winds.
● Install an outdoor unit against a wall if possible. If the site conditions cannot
meet the requirements and the local outdoor temperature may be below –
10°C, install a
bae plate by referring to the space requirements. The bae
plate height and width should be greater than or equal to the outdoor unit
height and width, respectively.
● If the site installation environment is complicated and the preceding
conditions are not met, contact Huawei technical support.
Space Requirements
Figure 4-18 Space requirements
4.2.4.5.2 Securing an Outdoor Unit
Prerequisites
● The M10 expansion bolts used for securing an outdoor unit have been
prepared.
● The concrete groundwork is prepared.
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide
Issue 02 (2020-12-25) Copyright © Huawei Technologies Co., Ltd. 80