At a high place with strong winds, install the outdoor unit against a wall to
ensure the normal operating of fans. Install a bae plate when necessary to
prevent the outdoor unit from toppling in strong winds.
Install an outdoor unit against a wall if possible. If the site conditions cannot
meet the requirements and the local outdoor temperature may be below –
10°C, install a
bae plate by referring to the space requirements. The bae
plate height and width should be greater than or equal to the outdoor unit
height and width, respectively.
If the site installation environment is complicated and the preceding
conditions are not met, contact Huawei technical support.
Space Requirements
Figure 4-18 Space requirements
4.2.4.5.2 Securing an Outdoor Unit
Prerequisites
The M10 expansion bolts used for securing an outdoor unit have been
prepared.
The concrete groundwork is prepared.
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide
Issue 02 (2020-12-25) Copyright © Huawei Technologies Co., Ltd. 80

Table of Contents

Other manuals for Huawei FusionModule500

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei FusionModule500 and is the answer not in the manual?

Huawei FusionModule500 Specifications

General IconGeneral
BrandHuawei
ModelFusionModule500
CategoryStorage
LanguageEnglish

Related product manuals