Figure 4-12 Layout for the scenario where the outdoor unit is placed higher than
the indoor unit
Figure 4-13 Layout for the scenario where the indoor unit is placed higher than
the outdoor unit
4.2.4.3 Installing an Indoor Unit
Procedure
Step 1 Remove the
ller panels from the 1st U to the 5th U of the cabinet.
Step 2 Push the indoor unit of the smart cooling product into the bottom of the cabinet
along the guide rails, and secure the indoor unit using M6 screws based on the
positions of
oating nuts on the cabinet mounting bars.
FusionModule500 Smart Mini Data Center
User Manual 4 Installation Guide
Issue 02 (2020-12-25) Copyright © Huawei Technologies Co., Ltd. 76