7.6 Daily checks before starting the Personal Protection System
Check the front screens of the Personal Protection System laser scanner for
contamination and clean as required (see page 240).
Cycle test (see page 243)
7.6.1 Cycle test
NOTICE
To ensure the correct operation of the personal protection system a cycle test must
be carried out after a 24 hour timer has expired or each time the truck is switched off
and on again.
u
The information message "9901" and the "Perform cycle test" symbol (130) prompt
you to perform the cycle test. During this time the travel speed is restricted to slow
travel (2,5 km/h).
u
The speed restriction is only removed when the cycle test has been performed.
Cycle test
Procedure
Switch off the truck.
Switch on the truck.
Z
When the truck is switched on the
display unit shows the “Acknowledge
cycle test” symbols (130,191).
Press (104) under the "Acknowledge
cycle test" symbol (191).
The truck automatically performs the
cycle test.
When the cycle test has been successfully performed:
The "Perform cycle test" symbol (130,191) fades out.
The speed restriction is removed.
The 2424 hour timer is reset and starts afresh.
The cycle test has been performed successfully.
130
191
104
243
04.19 en-GB

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Jungheinrich EFX 413 and is the answer not in the manual?

Jungheinrich EFX 413 Specifications

General IconGeneral
BrandJungheinrich
ModelEFX 413
CategoryTrucks
LanguageEnglish

Related product manuals