Published 2-23-2017, Control # 644-00
Standard Fabricated Counterweight
Removal
1. Rig the crane with three parts of line.
2. The standard fabricated counterweight may be lifted in
one of the following boom configurations.
3. Enter RCL code 1100. Refer to RCL Main Menu, page 3-
75.
4. Swing turntable to place the boom over the rear of the
crane.
5. Set the turntable lock pin in the down position.
6. Using the ECOS display, retract the locking cylinders
until the display indicates the cylinders are fully
retracted.
7. Lower the counterweight onto the carrier stands until the
display indicates the counterweight is fully lowered.
8. Rotate the cylinders to unlock from the counterweight.
9. Using the ECOS display raise the counterweight
cylinders from the tubes in the counterweight.
10. Swing the turntable to place the boom over-the-front.
11. Connect sling assembly to the standard counterweight
using the installation lifting holes (Figure 4-14).
12. Lift and place the counterweight onto the ground.
Boom Configuration
0-0-0-0-0
(30 ft radius)
0-0-0-0-50 0-0-0-50-0
FIGURE 4-14
Heavy 63,000 lb (28,577 kg) Counterweight
Standard 39,000 lb (17,690 kg) Counterweight
Counterweight Installation
Lifting Holes
Counterweight
Insert Lifting Eyes
Reference Only

Table of Contents

Other manuals for Manitowoc Grove RT9150E

Related product manuals