LED R&D Lab(VD)
201
Appendix 2 - S-Box Installation and Connection
① It is recommended to install it in a 19inch Server rack.
② Install so that the vents are open and do not turn sideways or overturn.
③ Be careful as blocking the ventilation holes may cause the product to overheat.
④ When installing multiple S-Boxes, install them at least 1U (44.45mm) away from the top product.
⑤ When installing on a wall, the product must be 10mm or more apart from the wall in the vertical, left and right,
and in the case of a cable port, install it 50mm or more apart for cable connection.
⑥ Keep the residual heat inside the rack below 35°C.
⑦ Be careful not to let liquids, etc., enter the product's ventilation holes.
• Cautions when installing S-Box (SNOWJAU/SNOWAAE)
SNOWJAU