2,3,4,5,6 While installing the CABINET, check if there is a step in the Z axis.
※ When a step occurs, use an absorber to open the gap between the CABINETs with the step difference. (Fig.1)
※ SEAM can be adjusted using the adjustment device of the vertical bar (using the 1.5mm wrench included in the frame kit).
※ The upper part controls the right and the lower part controls the left. (Fig. 2)
Fig.1 Check the Z-axis step and move it to the front with the adsorber
LED
2
Fig.2 Z-axis step adjustment
Un-Lock
Lock
Absorber
CABINET installation (IWA P1.26)
[ UHD SCREEN (36Cabinet) ]
5. Cabinet + Frame installation